Next steps
The GeoLaB project is divided into several project phases: The site exploration phase is currently underway, followed later by the laboratory implementation phase. Only then does the actual research begin.
Project phases| GeoLaB
Exploration phase
Seismic truck in operation on the Tromm. © GFZ
Drilling site with sound barrier on the Tromm. © KIT
In the exploration phase, scientists or specialist companies commissioned by them are conducting investigations in 2024 and 2025 in the areas of Wald-Michelbach, Grasellenbach and Rimbach. The goal is to answer the question: Is the area around the Tromm actually geologically suitable for the research laboratory? The results of all investigations will be summarized in a scientific site report. The decision on the geological suitability of the Tromm region is planned for late spring 2026.
Various investigations have been carried out and are planned, the approval of which will be applied for at the Hessian Mining Authority:
» Hydrological monitoring: Sampling and other measuring points relating to water for hydrogeological and hydrochemical data collection.
» Seismic monitoring: Passive monitoring of ground vibrations through seismometer measuring points.
» Seismics: Investigating the subsurface using sound waves generated by vibrations.
» Geophysical measurements: Additional surveys to determine, for example, the electrical and magnetic properties of the subsurface.
» Exploratory drilling: Drilling from the Tromm into greater depths to study the geological layers in more detail.
Seismics
Geophysics
Exploratory Drilling
Laboratory Implementation Phase
If the investigations during the exploration phase show that the Tromm area is a suitable research location, planning will continue. The laboratory implementation phase could start in 2026. After this decision about the “whether,” the concrete planning about the “how” begins. Only then does the planning and approval procedure start, which will be carried out with the utmost care and will therefore take additional months/years. Extensive permits are required. The approval proceeds as a multi-stage process under the Federal Mining Act (BbergG). Reviews and approvals are carried out by the Hessian mining authority.
During the laboratory implementation phase of the tunnel there may be disruptions for residents, for example due to noise or traffic. Ways are being sought to avoid traffic, for example by using the waste on site. As soon as it is clear when the construction site will be set up and what consequences this will have for local citizens, they will be informed directly.