Next steps
The GeoLaB project is divided into several project phases: The exploration phase is currently underway, followed later by the planing and construction phase. Only then does the actual research begin.
Project phases| GeoLaB
Exploration phase
Seismic truck in operation on the Tromm. © GFZ
Drilling site with sound barrier on the Tromm. © KIT
In the exploration phase, scientists are conducting investigations in 2024 and 2025 in the areas of Wald-Michelbach, Grasellenbach and Rimbach. The goal is to answer the question: Is the area around the Tromm actually geologically suitable for the research laboratory?
Various investigations are planned, the approval of which will be applied for at the Hessian Mining Authority:
» Groundwater monitoring: Sampling and other measuring points relating to water for hydrogeological and hydrochemical data collection.
» Seismic monitoring: Passive monitoring of ground vibrations through seismometer measuring points.
» Seismics: Investigating the subsurface using sound waves generated by vibrations.
» Geophysical measurements: Additional surveys to determine, for example, the electrical and magnetic properties of the subsurface.
» Exploratory drilling: Drilling from the Tromm into greater depths to study the geological layers in more detail.
Seismics
Geophysics
Site plan of the GeoLaB-1 exploratory borehole southwest of the Tromm natural playground. © KIT, aerial photo Tromm Google Maps, 2024
Construction site with drilling rig © KIT
First core from the GeoLaB-1 borehole on the Tromm © GeoLaB
Exploratory drilling
Drilling is being carried out on the Tromm to study the geological layers in more detail through exploratory drillings. The drilling site is located southwest of the nature playground on the Tromm. To significantly reduce noise emissions, the site has been enclosed with a 10-meter-high sound barrier.
The first borehole was drilled in February and March 2025 to a depth of about 500 meters. It was fully cored, meaning the extracted rock was preserved and recovered. These cores are now being thoroughly analyzed by GeoLaB researchers. For example, they are investigating the rock’s permeability (its ability to let fluids pass through) and its composition. After drilling, tests and measurements were carried out in April to further characterize the geological properties — in particular, to examine how fractured and water-permeable the subsurface is.
What did the first borehole reveal?
The findings are highly interesting for GeoLaB: over 500 meters of fractured granitoid rock were encountered. While data evaluation is still ongoing, researchers have already identified several fractured zones at various depths that indicate certain degrees of water permeability in the subsurface.
The second borehole
Because of the promising results of the first borehole, a second exploration borehole was drilled from the same site in June 2025. This second borehole was deviated — meaning it was drilled at an angle — reaching a depth of 585 meters and extending more than 350 meters horizontally. This allowed a broader section of the Tromm massif to be investigated.
Measurements from the borehole
The exploration boreholes not only provide direct insight into the Tromm’s rock and structure but can also be used for geophysical measurements. Sensors are installed directly in the borehole to collect valuable subsurface data.
Before these measurements can begin, the borehole must be prepared. During the week of August 4–8, the first borehole will be cleaned of cement residues. For this, the drilling rig will be set up again — but no new drilling will take place. The work serves solely to prepare the borehole technically for the upcoming measurements.
After the seconde borehole
Once the investigations around both boreholes are completed, the entire drilling site will be fully dismantled.
Planing and Construction Phase
If the investigations during the exploration phase show that the Tromm area is a useful research location, planning will continue. The construction phase starts in 2026 and extensive questions need to be answered:
» Where could the tunnel be built?
» How can the construction site and access be set up?
Of course, approvals from the Hessian Mining Authority as the responsible authority are also required. Finally, the tunnel for the GeoLaB research laboratory will be built into the mountain.
During the construction phase of the tunnel there may be disruptions for residents, for example due to noise or traffic. Ways are being sought to avoid traffic, for example by using the waste on site. As soon as it is clear when the construction site will be set up and what consequences this will have for local citizens, they will be informed directly.
The laboratory is set up in the tunnel. A visitor ramp and later an information pavilion are intended to make GeoLaB accessible to the population and visitors to the Tromm region and make the fascinating world beneath our feet visible. There will be regular events there by the GeoLaB team and the researchers involved.