Next steps
The GeoLaB project is divided into several project phases: with the decision on geological suitability, the site exploration phase is completed, followed by the planning and approval phase. Provided that approval is granted, this is followed by tunnel construction and a test operation phase, before the actual research operation is planned.
Project phases | GeoLaB
Exploration phase
Seismic truck in operation on the Tromm. © GFZ
Drilling site with sound barrier on the Tromm. © KIT
In the exploration phase, scientists or specialist companies commissioned by them conducted investigations in 2024 and 2025 in the areas of Wald-Michelbach, Grasellenbach and Rimbach. The goal was to answer the question: Is the area around the Tromm actually geologically suitable for the research laboratory? The results of all investigations have been summarized in a scientific site report. With the decision on geological suitability, the exploration phase has been completed.
Various investigations have been carried out and are planned, the approval of which will be applied for at the Hessian Mining Authority:
» Hydrological monitoring: Sampling and other measuring points relating to water for hydrogeological and hydrochemical data collection.
» Seismic monitoring: Passive monitoring of ground vibrations through seismometer measuring points.
» Seismics: Investigating the subsurface using sound waves generated by vibrations.
» Geophysical measurements: Additional surveys to determine, for example, the electrical and magnetic properties of the subsurface.
» Exploratory drilling: Drilling from the Tromm into greater depths to study the geological layers in more detail.
Seismics
Geophysics
Exploratory Drilling
Laboratory Implementation Phase
The exploratory phase has shown that the Tromm area is a suitable research site. However, a specific location has not yet been determined. Now, concrete planning for the rock laboratory is beginning, followed by an extensive permitting process. The parties involved are seeking a specific location for the access tunnel and planning the surface and underground infrastructure, tailored to local conditions. To this end, they are conducting further exploratory drilling and geophysical surveys. Extensive permits are required. The permitting process is a multi-stage procedure under the Federal Mining Act (BbergG). Reviews and approvals are carried out by the Hessian Mining Authority.
During the potential construction phase of the tunnel, residents may experience temporary disruptions, such as noise or traffic. Ways are being sought to keep traffic to a minimum.
Regular updates on the project’s progress will be provided, and the perspectives of the local community will be incorporated into the planning. The GeoLaB team is designing all structures to minimize impacts on people and the environment. The large-scale monitoring program already underway to protect drinking water and groundwater will continue.